THUNDER BAY — After 14 months of detouring around a broken culvert on River Street, it could still be another month before traffic is flowing smoothly again along the full length of the four-lane arterial road.
With new concrete footings all cured, a crane arrived to lift sections of a new steel arch into place over McVicar Creek. But even when that stage of the work is over, Vogrig said there's more to be done, meaning that the entire project won't be finished before mid-July at the earliest.
South Africa Latest News, South Africa Headlines
Similar News:You can also read news stories similar to this one that we have collected from other news sources.
These are the 5 headlines you should read this morningA report finds the grocery industry needs competition to help keep food prices down, a new strategy to attract digital talent to Canada and a supposed cage fight between billionaires.
Read more »
These are the 5 headlines you should read this morningRoseAnne Archibald has been ousted as national chief of the Assembly of First Nations, 'presumed human remains' are believed to be in the wreckage of the Titan, and special air quality statements continue.
Read more »
VIDEO: Seal regularly joining rowers on Abbotsford’s Sumas River - Terrace StandardFraser Valley Rowing Club has consistently seen the marine mammal in river since May
Read more »
Completion of Water Street Construction DelayedThe final phase of the Water Street infrastructure project, currently underway at Prescott Street and Job's Co...
Read more »