According to one researcher, 80 years of data have indicated that two out of 1,000 rail projects deliver on budget, schedule and benefits, and there\u0027s a…
“If you decide to build rail projects, you have the odds against you,” Bent Flyvbjerg, an expert in mega-projects, told the LRT inquiry commissioner during a panel discussion on Thursday.
Flyvbjerg, a researcher and author, has been an adviser to government and businesses. He’s a professorAdvertisement 3According to Flyvbjerg, 80 years of data have indicated that two out of 1,000 rail projects deliver on budget, schedule and benefits. He said there’s a 70-per-cent risk that a rail project will exceed the budget.
There has been $115 million in council-approved contingency spending on the project, increasing the cost to $2.245 billion for Stage 1. The railway was contracted to be done in May 2018, but it didn’t open until September 2019 after a significant construction delay. A sinkhole swallowed part of Rideau Street above the LRT tunnel in 2016.
Flyvbjerg also criticized using “bespoke” elements that haven’t been used in other projects during the discussion Thursday.There has been heavy scrutiny during the inquiry on the P3 approach to procuring the LRT project. The model required RTG to secure financing and meet milestones to unlock payments from the city. The contract continues during the maintenance period, with RTG’s maintenance affiliate receiving payments from the city based on LRT availability.
South Africa Latest News, South Africa Headlines
Similar News:You can also read news stories similar to this one that we have collected from other news sources.
LRT inquiry: Rail projects are a gamble with unfavourable odds for project owners, commissioner hearsAccording to one researcher, 80 years of data have indicated that two out of 1,000 rail projects deliver on budget, schedule and benefits, and there\u0027s a…
Read more »
LRT INQUIRY: Rail projects are a gamble with unfavourable odds for project owners, commissioner hearsAccording to one researcher, 80 years of data have indicated that two out of 1,000 rail projects deliver on budget, schedule and benefits, and there\u0027s a…
Read more »
Ottawa LRT system resumes full service after lightning strikeFull service resumed on Ottawa's light rail transit system Friday afternoon, four-and-a-half days after a lightning strike reduced service on the system.
Read more »
Two companies shortlisted for first phase of Green Line LRT project - Calgary | Globalnews.caBow Transit Connectors and City Link Partners now move to the request for proposal stage, where they will compete to become development partners of Calgary's Green Line project.
Read more »
OC Transpo boss reports 'progress' on LRT repairs, full service still expected FridayTranspo boss Renée Amilcar said Thursday the agency was making progress on restoring LRT service and expects it to be back at full service on Friday.
Read more »