ESKOM LIVE | Stage 4 to continue until further notice, but beware of 'erratic' load shedding changes | News24_Business
Eskom announced on Friday afternoon that the Stage 4 load shedding it implemented in the early hours of the morning will continue until further notice
There is 4 887MW out on planned maintenance, while another 15 320MW of capacity is unavailable due to breakdowns"Stage 4 load shedding was implemented at 05:26 this morning until further notice," spokesperson Sikonathi Mantshantsha said. He said those municipalities that owed Eskom needed to consider their role in causing more load shedding.
There are expectations from government and Eskom’s new chair Mpho Makwana for the utility to hit a 75% energy availability factor soon."Where we find ourselves now, it looks like a steep hill … However, we need additional capacity, in order for generation colleagues to properly maintain their plants," Oberholzer said.
However, we need additional capacity, in order for generation colleagues to properly maintain their plants.
South Africa Latest News, South Africa Headlines
Similar News:You can also read news stories similar to this one that we have collected from other news sources.
ESKOM LIVE | Load shedding jumps to Stage 4 | Fin24All the latest news and analysis on load shedding, power and the national grid.
Read more »
Eskom secures R180m for new training facility at Grootvlei power station - De Ruyter | Fin24Eskom has secured about R180 million in funding from the German development bank, KfW, to set up a renewable energy training facility at the Grootvlei coal power station. | News24_Business
Read more »
Loadshedding: Eskom announces stage 4 until further noticeStage 4 loadshedding has been implemented due to further breakdowns amounting to 17 056MW of generation capacity, low pumped storage dam levels and lack of diesel.
Read more »
Eskom implements stage 4 load shedding until further noticeThe power utility cited breakdowns - among others - resulting in decimated generation capacity for its latest power cut notice.
Read more »
Eskom announces stage four load shedding | The CitizenThere's been further breakdowns amounting to 17 056MW of generation capacity, low pumped storage dam levels and lack of diesel. Eskom loadshedding To shed light🔦
Read more »